Key takeaways

  • Keep blocks moist for at least 7 days; strength keeps growing to 28 days.
  • Cover fresh blocks with plastic sheeting to stop rapid drying in hot, windy climates.
  • Steam curing at 60–70 °C can reach handling strength in 12–24 hours for high-output plants.
  • Never stack blocks until they reach handling strength.

Cement needs water to hydrate. If a fresh block dries too fast, hydration stops at the surface: corners crumble, the face dusts and strength can drop by a third. Curing keeps blocks moist and warm long enough for the cement to develop strength.

The three stages

  1. Initial set (0–24 h): blocks stay on pallets, protected from sun, wind and rain.
  2. Moist curing (1–7 days): blocks are de-palleted, stacked loosely and kept damp.
  3. Air curing (7–28 days): blocks continue to gain strength in storage before delivery.

Natural curing with sprinkling

The simplest method: spray water two to four times a day. It works in mild climates but uses a lot of water and is easy to neglect at weekends.

Covered curing

Wrapping stacks in plastic sheeting traps moisture and heat. It is the best low-cost improvement for hot or windy sites and reduces water use by more than half.

Steam curing

Automatic plants such as the QT12-15 often use curing chambers heated with low-pressure steam at 60–70 °C. Blocks reach handling strength in 12–24 hours, freeing up pallets and space. Raise and lower temperature gradually (about 15–20 °C per hour) to avoid thermal cracking.

Curing egg-laid blocks

Blocks made with a mobile egg-laying machine cure on the floor where they are laid. Shade nets and regular sprinkling are essential because there is no pallet underneath to retain moisture.

Common mistakes

  • Stacking blocks too soon — causes cracked corners.
  • Letting blocks dry in direct sun on day one.
  • Delivering blocks at 3 days to meet demand — strength may be half the 28-day value.

Frequently asked questions

How long should concrete blocks cure before use?

At least 7 days of moist curing, and ideally 14–28 days before use in load-bearing walls.

Is steam curing necessary?

No. It is worth it for high-output plants where pallets and space are limited, or in cold climates.

Brick Machine Factory Engineering Team

Sales and process engineers who design block, paver and CEB plants and commission them on site. About us

Free plant proposal

Tell us your target output. We’ll design the plant.

Send your block sizes, daily output and power supply. A sales engineer replies within 24 hours with a configuration, layout and quotation.

Send an inquiry

Reply within 24 hours, Mon–Sat.